DEC Projects and Nasi Civil Complete Challenging Melbourne Water Project

DEC Projects and Nasi Civil have been doing some great work on Melbourne Water assets at Level Crossing Removal Project jobs.

This one was a tricky 7.5m deep excavation and micro-tunnelling 50m to a 6m deep exit pit. Both ends needed large in-situ pits constructed that got dug out with a 30t machine with a quick hitch boom attachment to get that extra depth needed.

All finished and ready for handed over now. The team did an outstanding job, bring excellent innovation to the project along the way.

Previous
Previous

Welcome to Our Team

Next
Next

North Williamstown Station Level Crossing Removal Project